Hiram's WellStar Hospital Celebrates Completion of Top Floor

Hiram's WellStar Paulding Hospital is on schedule to see first patients in April 2014.

Brasfield & Gorrie celebrated the completion of the structure’s top floor, of WellStar Paulding Hospital located in Hiram.

When completed, the hospital will be seven stories and 295,000 sq ft. Also being constructed as part of this project are a 120,000 sq ft precast parking deck and a four-story, 82,220 sq ft medical office building. The hospital will house emergency exam rooms, pediatric emergency exam rooms, surgery suites, decentralized nursing stations, patient rooms, administrative offices, and a café.

This is Brasfield & Gorrie’s 52nd project with WellStar Health System. CDH Partners, Inc., is the project architect.

Find out what's happening in Dallas-Hiramwith free, real-time updates from Patch.

WellStar Paulding Hospital broke ground in January 2012, and Brasfield & Gorrie completed geothermal drilling on the facility in November 2012.The hospital will be one of the nation’s first to be conditioned solely by geothermal energy.

WellStar Paulding Hospital is expected to open its doors to patients in April 2014.

Find out what's happening in Dallas-Hiramwith free, real-time updates from Patch.

“We are excited to reach the topping out mark and see significant progress on WellStar Paulding Hospital. Our relationship with WellStar has always been collaborative and strong, and we appreciate the opportunity to continue working with them. Our goal is to deliver a state-of-the-art facility that goes beyond meeting the healthcare needs of the Paulding community,” said Tate McKee, Vice President and Division Manager at Brasfield & Gorrie.